Request
Please provide the following information relating to solar photovoltaic (PV) installations on buildings or carparks owned or occupied by the Council.
For the purposes of this request, include PV installations on operational buildings, schools, depots, leisure facilities, car parks/carports and other Council-owned properties.
Strategy and Plans
1. Does the Council have a documented plan, programme, strategy or approved business case relating to the installation of rooftop solar PV on its estate?
If yes, please provide:
- The title of the document(s)
- The approval date
- A copy of the document(s) or a web link where available
2. What stage best describes the Council's current rooftop solar programme?
Please indicate all that apply:
- No current plans
- Initial opportunities identified
- Feasibility studies underway
- Business case(s) approved
- Funding secured
- Procurement underway
- Installers appointed
- Installation programme underway
- Pipeline and Timescales
3. Does the Council currently have a pipeline of future rooftop solar projects?
If yes, please provide:
- Number of buildings identified
- Number of buildings assessed for feasibility Number of buildings approved for installation Total MW of installed solar aimed for.
4. Please provide the anticipated timescales for delivery of planned rooftop solar projects, including:
- Projects expected within 12 months
- Projects expected within 1-3 years
- Projects expected beyond 3 years
- Funding and Budget
5. Has the Council allocated capital budget for future rooftop solar installations?
If yes, please provide:
Budget amount allocated (or budget range if exact figures cannot be disclosed) Financial year(s) covered
6. What funding sources does the Council expect to use for planned rooftop solar projects?
Please indicate all applicable sources:
- Existing capital budget
- Capital receipts
- Prudential borrowing
- PWLB borrowing
- Public Sector Decarbonisation Scheme
- Great British Energy funding
- Community energy investment
- Power Purchase Agreement (PPA) or third-party finance Other (please specify)
7. Does the Council currently have a formal relationship, partnership, memorandum of understanding, framework agreement or active project with any Community Energy organisation?
If yes, please provide:
- Name of the organisation(s)
- Nature of the relationship
- Whether rooftop solar forms part of that relationship Procurement and Delivery
8. Has the Council already procured, appointed or framework-selected one or more suppliers for future rooftop solar delivery?
If yes, please provide:
- Supplier name(s)
- Procurement route used
- Contract start and end dates (where available)
9. For future rooftop solar projects not yet procured, what procurement route does the Council currently expect to use?
Please indicate all that apply:
- Open tender
- Framework agreement
- Dynamic Purchasing System
- Not yet determined
10. If a framework route is expected to be used, please identify the framework(s) being considered.
Decision-Making
11. Has the Council undertaken rooftop solar feasibility studies, condition surveys or estate-wide solar opportunity assessments within the past three years?
If yes, please provide:
- Date completed
- Number of sites assessed
- Copies of reports where available
12. What are the principal barriers currently preventing faster deployment of rooftop solar across the Council estate?
For example:
- Funding constraints
- Roof condition
- Grid capacity
- Internal resources
- Planning or heritage constraints
- Competing capital priorities
- Other reasons
13. Please identify the Council officer, team or department with primary responsibility for the development and delivery of rooftop solar PV projects across the Council estate.
- Job title
- Service/team name
- Email address or contact point
14. Please provide the name of the officer or team responsible for procuring solar PV installations and associated professional services.
- Job title
- Service/team name
- Email address or contact point
Response
1. No.
2. No current plans.
3. No.
4. Not applicable.
5. No.
6. Not applicable.
7. No.
8. No.
9. Not applicable.
10. Not applicable.
11. No.
12. As follows:
- Funding constraints
- Competing capital priorities
13. The Council does not hold this information.
14. The Council does not hold this information.