FI15548

Request

  1. The number of major housing developments (10 or more dwellings) in your jurisdiction which were completed between the years 2021-2025 inclusive which had a Section 106 (Town and Country Planning Act 1990) planning obligation.
  2. Of these completed developments, the number which changed the stipulations of their S106 obligations, or did not provide them, by the time of completion.
  3. For these, please provide the following:
    1. The name of the development, the developer name, and original planning permission reference.
    2. The obligations the developer agreed to as part of the Section 106 to the council upon initial planning permission being granted.
    3. A summary of the final delivery (including built property or financial contributions) provided by the developer to fulfil the Section 106 agreement, upon completion of the building contract.
    4. Any reasons given by the developer for any difference between the initial agreement and final delivery.
    5. If any developer did not provide anything by way of fulfilment of the Section 106 agreement, please summarise any further action taken by the council, including but not limited to litigation, requiring a replacement contribution of any kind, such as a financial contribution, discontinuing the building project, etc. Please provide this data in an excel spreadsheet.

Response

1. Please note, site survey data has not been collected for 2024-25 and is therefore unavailable.  All the Financial obligations secured in the S106's have been received.  To view all planning applications and the S106 please use the online portal at https://publicaccess.dover.gov.uk/online-applications/search.do?action=simple&searchType=Application 

Monitoring Year Development Completed 

2021/22: 

17/00826 - 13/02/19

17/00892 - 07/09/18

16/00017 - 12/02/18

17/00387 - 21/03/18

18/01119 (Aylesham Village Expansion S73 19/00821)*

19/00025 (Aylesham Village Expansion S73 19/00821)* 

2022/23: 

19/00403 - 06/02/20

18/00681 - 14/09/20

16/01247 - 31/07/22

20/00384 (Aylesham Village Expansion S73 19/00821)*

18/00682 - 18/10/19

21/00209 - 06/02/20

18/00681 - 14/09/20

21/01080 - 23/02/21 

2023/24: 

20/01508 - 20/07/22

16/01049 - 15/02/24

15/01184 - 01/10/16

19/00243 - 19/12/19 

* Please note the S106 for Aylesham Village Expansion is still active, and is linked to the Section 73 application 19/00821, from which subsequent Reserved Matters applications have been granted.

2. There are no completions on Major developments (10+dwellings)  between 2021 and 2023 that have outstanding S106 financial obligations. 

Further information on S106 financial obligations received during each monitoring year is available on our website via the Infrastructure Funding Statements (IFS) which are available at https://www.dover.gov.uk/Planning/Planning-Policy/Infrastructure-Delivery-and-S106-Obligations/Home.aspx.

3. There are no completions on Major developments (10+dwellings)  between 2021 and 2023 that have outstanding S106 financial obligations. 